Grafton Communal Water System - Water Meter Replacement Program. Replacement of existing 227 residential and 20 commercial water meters with new water meters on and around 10836 County Road #2.
Federal contribution
$41,688
Federal share50%
of $83.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Alnwick/Haldimand
- Construction start
- Jun 15, 2018(actual)
- Construction end
- Jul 14, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast May 31, 2017
- Construction end6 months lateforecast Dec 31, 2017