Robert Adams Pond Rehabilitation and Sediment Cleanout including Removal of approximately 1,200m3 of sediment

Clarington, Ontario

completeWastewaterCWWF
Federal contribution
$129,817
Federal share48%

of $270.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 28, 2017
ApprovedMar 27, 2018
201720182019
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 1, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction end9 months lateforecast Sep 15, 2018