Replacement of 1750 metres of ductile watermain in the Robinson subdivision, Angus
Federal contribution
$413,471
Federal share49%
of $845.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Essa
- Construction start
- Oct 1, 2017(actual)
- Construction end
- Sep 26, 2019(actual)
Against the original forecast
- Construction start3 months earlyforecast Jan 4, 2018
- Construction end6 months lateforecast Mar 31, 2019
Also in Essa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50116 in the federal list. How to read these figures.