Restoration of the Salle des Habitants
Federal contribution
$102,357
Federal share33%
of $307.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of L'Islet
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Oct 9, 2019(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2017
- Construction end21 months lateforecast Dec 31, 2017