Restoration of the Salle des Habitants

L'Islet, Quebec

completeCultureSCF
Federal contribution
$102,357
Federal share33%

of $307.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of L'Islet
Construction start
Nov 1, 2017(actual)
Construction end
Oct 9, 2019(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2017
  • Construction end21 months lateforecast Dec 31, 2017