Back to projects

Extension of the water supply and sewer infrastructure - Pionniers Road East / Petit-Moulin area

L'Islet, Quebec

completeWastewaterCWWF
Federal contribution
$1.5M
$1,514,999
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of L'Islet
Construction start
May 23, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2018

Also in L'Islet