Riprap of the Rue du Bord-de-l'Eau
Federal contribution
$45,121
Federal share33%
of $135.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2018
20182019202020212022
Built
Approved 15 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Grande-Rivière
- Construction start
- Jul 14, 2017(actual)
- Construction end
- Nov 29, 2021(actual)
Against the original forecast
- Construction end4.3 years lateforecast Aug 11, 2017