Water Systems Extension (du Moulin Street Sector)

Grande-Rivière, Quebec

completeDrinking WaterGIS
Federal contribution
$1.2M
$1,238,400
Federal share40%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Grande-Rivière
Construction start
Oct 7, 2021(actual)
Construction end
Feb 10, 2023(actual)

Against the original forecast

  • Construction end6 months lateforecast Aug 1, 2022