Water Systems Extension (du Moulin Street Sector)
Federal contribution
$1.2M
$1,238,400
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Grande-Rivière
- Construction start
- Oct 7, 2021(actual)
- Construction end
- Feb 10, 2023(actual)
Against the original forecast
- Construction end6 months lateforecast Aug 1, 2022
Also in Grande-Rivière
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56752 in the federal list. How to read these figures.