Airport Expansion and Upgrade

Rouyn-Noranda, Quebec

completeRegional And Local AirportsSCF
Federal contribution
$12.4M
$12,397,982
Federal share33%

of $37.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2017
2016201820202022
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Rouyn-Noranda
Construction start
Dec 21, 2015(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction start2 years earlyforecast Jan 1, 2018
  • Construction end9 months lateforecast Sep 1, 2021

Also in Rouyn-Noranda

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50153 in the federal list. How to read these figures.