Water purification - Quartier Cléricy
Federal contribution
$1.5M
$1,529,998
Federal share45%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 6, 2017
20172018
Built
Approved 7 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Rouyn-Noranda
- Construction start
- Aug 4, 2017(actual)
- Construction end
- Oct 26, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2017
- Construction end5 months earlyforecast Mar 31, 2019
Also in Rouyn-Noranda