Water purification - Quartier Cléricy

Rouyn-Noranda, Quebec

completeWastewaterCWWF
Federal contribution
$1.5M
$1,529,998
Federal share45%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 6, 2017
20172018
Built

Approved 7 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Rouyn-Noranda
Construction start
Aug 4, 2017(actual)
Construction end
Oct 26, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2019

Also in Rouyn-Noranda

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48806 in the federal list. How to read these figures.