Replacement of lids on the digester tanks at Waste Water Treatment Facility at 92 Alexandra Avenue, Point Edward

Point Edward, Ontario

underwayWastewaterCWWF
Federal contribution
$174,951
Federal share39%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018202020222024
BuiltForecast
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Point Edward
Construction start
Apr 2, 2018(actual)
Construction end
Sep 30, 2024(forecast)

Against the original forecast

  • Construction start13 months lateforecast Mar 1, 2017