Upgrade of Flow Meter Installation and Construction of a Protective Insulated Building
Federal contribution
$9,300
Federal share47%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Thornloe
- Construction start
- Sep 15, 2019(actual)
- Construction end
- Oct 16, 2019(actual)
Against the original forecast
- Construction start2.2 years lateforecast Jul 1, 2017
- Construction end2 weeks earlyforecast Oct 31, 2019