Rehabilitation of the existing watermain with new polyvinyl chloride materials on King Street West (#40-#94) that serves the Millbrook Community

Cavan-Monaghan, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share8%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Cavan Monaghan
Construction start
Aug 1, 2017(actual)
Construction end
Dec 13, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end2 months lateforecast Sep 30, 2017

Also in Cavan-Monaghan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50243 in the federal list. How to read these figures.