New Construction of 3 drilled wells at three public facilities within Whitney

South Algonquin, Ontario

completeDrinking WaterCWWF
Federal contribution
$28,900
Federal share41%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of South Algonquin
Construction start
Jul 31, 2019(actual)
Construction end
Aug 28, 2020(actual)

Against the original forecast

  • Construction start2.2 years lateforecast May 1, 2017
  • Construction end13 months earlyforecast Sep 30, 2021

Also in South Algonquin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50246 in the federal list. How to read these figures.