Bus replacements standard buses (36)
Federal contribution
$10.0M
$10,015,086
Federal share50%
of $20.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2017
2017
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Jun 1, 2017(actual)
Also in Québec