Upgrade Supervisory Control And Data Acquisition (SCADA) systems for Cochenour Water Treatment Plant, Balmertown Reservoir Pumping Station and Madsen Water Treatment Plant

Red Lake, Ontario

completeDrinking WaterCWWF
Federal contribution
$158,028
Federal share50%

of $316.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 17, 2017
ApprovedFeb 26, 2018
2018
Built

Approved 7 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Red Lake
Construction start
Nov 30, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 1, 2017