System-Wide Main Water Valves Rehabilitation and Replacement
Federal contribution
$15,000
Federal share50%
of $30.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
2018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Local Services Board of Gogama
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Dec 4, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 1, 2017
- Construction end5 weeks lateforecast Oct 31, 2018
Also in Gogama
- Replacement of Back Up Pump House Generator and Lagoon Expansion$1.4M
- Upgrades to Wastewater Treatment System$21.0K
- Consultation for repair/cleaning of concrete water holding tanks at Water Distribution/Generator Building$18.0K
- Monitoring Equipment Upgrades at Water Distribution/Generator Building$5.8K
- Wastewater Lagoon Cells Clean Up$5.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50292 in the federal list. How to read these figures.