Back to projects

System-Wide Main Water Valves Rehabilitation and Replacement

Gogama, Ontario

completeDrinking WaterCWWF
Federal contribution
$15,000
Federal share50%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2018(actual)
Construction end
Dec 4, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 1, 2017
  • Construction end5 weeks lateforecast Oct 31, 2018

Also in Gogama