Crowning and Hard-topping of O'Gemaa Miikan storm water system

Beausoleil First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$62,659
Federal share50%

of $125.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019202020212022
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Beausoleil First Nation
Construction start
Jan 1, 2019(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction start21 months lateforecast Apr 1, 2017
  • Construction end9 months earlyforecast Sep 20, 2022