Rehabilitation of tracks at the Lachine Maintenance Centre
Federal contribution
$460,718
Federal share50%
of $921.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 15, 2017
20172018
Built
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport métropolitain (RTM)
- Construction start
- Oct 11, 2016(actual)
- Construction end
- Jun 22, 2018(actual)
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50302 in the federal list. How to read these figures.