Back to projects

ITS measures and client information – Chrono Phase 5

Montréal, Quebec

completePublic TransitPTIF
Federal contribution
$2.2M
$2,185,275
Federal share50%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2017
20182019
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 1, 2017(actual)
Construction end
Jul 31, 2019(actual)

Also in Montréal