VISSIM licence
Federal contribution
$16,251
Federal share50%
of $32.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 15, 2017
20172018
Built
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Agence métropolitaine de transport (AMT)
- Construction start
- Jun 2, 2016(actual)
- Construction end
- Feb 15, 2018(actual)
Also in Montréal