Renewal of service vehicle fleet

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$541,138
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 18, 2017
2018202020222024
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 1, 2017(actual)
Construction end
Sep 30, 2023(actual)

Also in Québec