Repairs at the Les Saules, Charlesbourg and Beauport stations

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$125,000
Federal share50%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 18, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Dec 17, 2017(actual)
Construction end
Mar 31, 2020(actual)