Chapleau Objibwe First Nation water treatment plant equipment upgrade
Chapleau Ojibwe First Nation, Ontario
Federal contribution
$43,614
Federal share42%
of $102.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
2018
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Chapleau Ojibwe First Nation
- Construction start
- Dec 29, 2017(actual)
- Construction end
- Oct 8, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast Feb 1, 2017
- Construction end6 months lateforecast Mar 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50331 in the federal list. How to read these figures.