Implementation and deployment of the new bus network in conjunction with the implementation of the bus rapid transit (BRT)

Québec, Quebec

completePublic TransitPTIF
Federal contribution
$297,500
Federal share50%

of $595.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 16, 2018
201820192020
Built

Approved 9 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Sep 1, 2017(actual)
Construction end
Mar 31, 2020(actual)