Bus travel study
Federal contribution
$495,000
Federal share50%
of $990.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2017
2017201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50350 in the federal list. How to read these figures.