Repairs and Upgrades at Water Treatment Plant

Pays Plat First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$53,127
Federal share50%

of $106.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 10, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 6 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Pays Plat First Nation
Construction start
Dec 11, 2017(actual)
Construction end
May 31, 2020(actual)

Against the original forecast

  • Construction start10 months lateforecast Feb 1, 2017
  • Construction end16 months earlyforecast Sep 30, 2021

Also in Pays Plat First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50357 in the federal list. How to read these figures.