Fare sale and control system Mobile payment
Federal contribution
$251,042
Federal share50%
of $502.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2017
20182019202020212022
Built
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Jun 1, 2018(actual)
- Construction end
- Jul 31, 2022(actual)