Replacement of a service vehicle Commissioner
Federal contribution
$27,505
Federal share50%
of $55.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Nov 8, 2017(actual)
Also in Longueuil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50374 in the federal list. How to read these figures.