Back to projects

Upgrade Seasonal Water lines and Wastewater lines to heated lines for Year round accessibility throughout property

Missanabie Cree First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$12,318
Federal share19%

of $64.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2018(actual)
Construction end
Dec 2, 2018(actual)

Against the original forecast

  • Construction start16 months lateforecast May 29, 2017
  • Construction end11 months lateforecast Dec 31, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50375 in the federal list. How to read these figures.