Equipment upgrade program

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$113,882
Federal share50%

of $227.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Feb 12, 2018(actual)
Construction end
Dec 31, 2019(actual)

Also in Longueuil