Upgrade of the fuel system
Federal contribution
$23,170
Federal share50%
of $46.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Réseau de transport de Longueuil (RTL)
- Construction start
- Apr 30, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Also in Longueuil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50386 in the federal list. How to read these figures.