Upgrade of the fuel system

Longueuil, Quebec

completePublic TransitPTIF
Federal contribution
$23,170
Federal share50%

of $46.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 30, 2018(actual)
Construction end
Mar 31, 2020(actual)