Cataraqui Trail - Sydenham and Camden East Trail Improvement
Federal contribution
$18,500
Federal share49%
of $37.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Cataraqui Region Conservation Authority: CRCA
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Glenburnie