Cataraqui Trail Trailhead, Bridge and Surface Improvements
Federal contribution
$25,000
Federal share36%
of $69.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Cataraqui Region Conservation Authority: CRCA
- Construction start
- Jun 1, 2015(actual)
- Construction end
- Dec 4, 2015(actual)