Lake Lillian and Mount Swansea Trail Network Improvements
Federal contribution
$12,500
Federal share27%
of $46.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Columbia Valley Cycling Society: CVCS
- Construction start
- Mar 16, 2015(actual)
- Construction end
- Dec 4, 2015(actual)
Also in Invermere
- Nzen'man' Bird's Nest$8.5M
- Paddy Ryan Water Treatment Plant UV Disinfection Upgrade$908.5K
- Invermere - Toby Creek Dike Improvements$883.6K
- Invermere - Climate Change Mitigation and Flooding/Stormwater Management Improvements$629.4K
- Columbia Valley Greenways Trail Alliance - Markin-MacPhail Westside Legacy Trail$540.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50495 in the federal list. How to read these figures.