Back to projects

Repair of the Trail

Rigaud, Quebec

completeRecreationNRT
Federal contribution
$2,660
Federal share50%

of $5.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Rigaud

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50564 in the federal list. How to read these figures.