Repair of the roof of the D Wing
Federal contribution
$236,000
Federal share80%
of $295.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Ouest
- Construction start
- Apr 19, 2021(actual)
- Construction end
- Sep 30, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 1, 2021
- Construction end2 months earlyforecast Dec 1, 2021
Also in Rigaud