PSS Installation

Woodstock, New Brunswick

completeRecreationNRT
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
20152016
Built

Approved 16 months before the announcement.

Program
National Recreational Trails Program
Construction start
Dec 10, 2014(actual)
Construction end
Oct 15, 2015(actual)

Also in Woodstock