New Well House & Water Transmission Main
Federal contribution
$960,000
Federal share40%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20212022
Built
Approved 14 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Woodstock
- Construction start
- Jul 6, 2020(actual)
- Construction end
- Dec 13, 2021(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2020
- Construction end3 months earlyforecast Feb 28, 2022
Also in Woodstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57019 in the federal list. How to read these figures.