Back to projects

Trout Lake Bridge Replacement

Truro, Nova Scotia

completeRecreationNRT
Federal contribution
$31,625
Federal share50%

of $63.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Fundy Trail Snowmobile Club
Construction start
Jul 13, 2015(actual)
Construction end
Aug 18, 2015(actual)

Also in Truro

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50716 in the federal list. How to read these figures.