Back to projects

Meewasin Valley Trail - Northeast Expansion

Saskatoon, Saskatchewan

completeActive TransportationNRT
Federal contribution
$81,056
Federal share50%

of $162.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Meewasin Valley Authority
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50769 in the federal list. How to read these figures.