Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- City of Moose Jaw
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)