Dagmar North Trail
Federal contribution
$20,000
Federal share49%
of $41.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Durham Mountain Biking Association: DMBA
- Construction start
- Apr 15, 2015(actual)
- Construction end
- Dec 21, 2015(actual)
Also in Uxbridge