Back to projects

Creating a Network of Positive Trail Experiences

Toronto, Ontario

completeRecreationNRT
Federal contribution
$23,800
Federal share27%

of $89.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 13 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Ontario Nature
Construction start
Apr 1, 2015(actual)
Construction end
Dec 14, 2015(actual)

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50851 in the federal list. How to read these figures.