Creating a Network of Positive Trail Experiences
Federal contribution
$23,800
Federal share27%
of $89.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Ontario Nature
- Construction start
- Apr 1, 2015(actual)
- Construction end
- Dec 14, 2015(actual)
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50851 in the federal list. How to read these figures.