CCCA Trail Rehabilitation and Promotion
Federal contribution
$14,000
Federal share50%
of $28.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Catfish Creek Conservation Authority
- Construction start
- May 1, 2015(actual)
- Construction end
- Dec 31, 2015(actual)
Also in Springwater
- Installation of Mechanical Ventilation; Ventilation Improvement; Portable Unit Ventilator; Portable Replacement; Portable Refurbishment$7.7M
- Ventilation Improvement; Sanitizing Station$3.0M
- Improvements to Highway 400 Detour Routes - Wilson Drive$816.7K
- Bottle Filling Stations; Touchless Door Open Devices$575.0K
- Queen Street East$437.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50869 in the federal list. How to read these figures.