District 15 - Project 4 TOP Project - Northern Corridor Du Nord - Kapuskasing Improvement
Federal contribution
$5,188
Federal share50%
of $10.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Ontario Federation of Snowmobile Clubs: OFSC
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Kapuskasing
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50889 in the federal list. How to read these figures.