Trail Route 125 - Project 2
Federal contribution
$39,240
Federal share40%
of $98.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Paradis du Quad Ouareau
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Saint-Donat