Construction of a bridge on Trans-Quebec Trail 33
Federal contribution
$9,930
Federal share50%
of $19.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Club Moto-Neige Saint-Donat Inc.
- Construction start
- Oct 1, 2015(actual)
- Construction end
- Dec 15, 2015(actual)