Preliminary Study of the Trail Development Plan for Highway 10, 10-55 and 50
Federal contribution
$31,000
Federal share42%
of $73.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
20152016
Built
Approved 16 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Fédération Québécoise des Clubs Quads: FQCQ
- Construction start
- Nov 25, 2014(actual)
- Construction end
- Dec 9, 2015(actual)
Also in Montréal