Trail B Repairs - Madawaska to Whitney
Federal contribution
$176,205
Federal share50%
of $353.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Renfrew County ATV Inc.
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension$1.9M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50979 in the federal list. How to read these figures.