Toward New Horizons 2009

Sherbrooke, Quebec

completeActive TransportationNRT
Federal contribution
$42,259
Federal share49%

of $85.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2009
2010
Built

Approved 2 months before the announcement.

Program
National Recreational Trails Program
Ultimate recipient
Sentiers de l'Estrie Inc.
Construction start
May 26, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Sherbrooke

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51017 in the federal list. How to read these figures.